Six weeks, one project lead.
From the first call to the final handover you deal with one named person. Here is exactly what happens, what we need from you and what you get at each stage.
Week 0
Call & survey
What happens
A 15-minute call, then an engineer visits for about an hour. Drone flight, loft and roof check, meter photo.
What we need from you
Twelve months of bills and access to the loft.
What you get
Roof model and shading report.
Week 1
Design & fixed quote
What happens
We lay out every panel, model the shading hour by hour and size the battery against your real usage.
What we need from you
A 30-minute review call.
What you get
Fixed-price quote with a year-one output figure.
Weeks 2–4
Permits & grid
What happens
We file structural sign-off and the grid connection application, and book the scaffold.
What we need from you
Sign two forms. That is it.
What you get
Approval letters and an install date.
Week 5
Install day
What happens
Scaffold goes up the day before. Rails, panels, inverter and battery are fitted in one or two days.
What we need from you
Keep the driveway clear.
What you get
Daily photo updates from the crew lead.
Week 6
Switch-on & handover
What happens
Inspection, commissioning, app setup and a walk-through of the isolators and warranty pack.
What we need from you
Thirty minutes for the handover.
What you get
Warranty pack and live monitoring.
Years 1–25
Aftercare
What happens
We watch output remotely and call you if anything drifts. Free annual health check in year one.
What we need from you
Nothing, unless you want a chat.
What you get
A production guarantee report each spring.

Our own crews
No subcontractors on your roof.
Every installer is employed by Tiltyard, trained in-house and certified for working at height. The same crew lead who walks your roof on install day signs off the job.
Scaffold inspected before anyone climbs
Roof photographed before and after
Site swept and every offcut taken away